| EMPLOYER | : | Park Holding-Eti Soda A.Ş. |
| PROJECT NAME | : | Beypazarı Trona Facilities Mechanical Installation Works and Storage Tanks |
| PROJECT LOCATION / DATE | : | Ankara / 2008 |
| PROJECT DURATION | : | 240 Days |
| PROJECT DETAIL | : | 6 X 2.000 m³-2 X 1.000 m³-2 X 200 m³ Storage tanks with a total capacity of 14,400 m³. Manufacturing-Assembly-Painting-Cathodic protection-Grounding-Lighting-Isolation and tank instruments. Main pump station steel fabrication and pipe bridges manufacturing, assembly and painting. A total of 12,000 mt of mechanical piping and all insulation works on site. |