TPAO 1 ADET 150.000 BBL KAPASİTELİ SİLİNDİRİK DİKEY TANK BORULAMA SİSTEMİ YAPIM İŞİ-BATMAN TERMİNALİ- BATMAN-2021

TPAO 1 ADET 150.000 BBL KAPASİTELİ SİLİNDİRİK DİKEY TANK BORULAMA SİSTEMİ YAPIM İŞİ-BATMAN TERMİNALİ- BATMAN-2021
EMPLOYER:TÜRKİYE PETROLLERİ ANONİM ORTAKLIĞI (TPAO)
PPROJECT NAME :Batman Terminal 1 Piece 150000 BBL Capacity Cylindrical Vertical Tank Piping System Construction Work
PROJECT LOCATION / DATE:BATMAN-TÜRKİYE / 2021
PROJECT DURATION:450 Days
PROJECT DETAIL:Manufacturing-Installation Works, Tank Foundation, Ground Improvement Works for 1 X 25.000 m3 Floating Roof Tank, All Site Mechanical Piping and Construction Works