info@silverteknik.com
+90 312 395 7617-18
Online Catalog
Homepage
Corporate
About Us
Vision & Mission
Quality Certificates
Human Resources
References
Online Catalog
Projects
In Process Projects
Finished Projects
Machine park
Pre-Production
Field Applications
Field of Activities
Industrial Plant Installations
Mechanical Assembly Work
Pre-Production
Field Applications
Assembly of Machinery Equipment
Mechanical Pipework
Electric-Automation Works
Construction Works
Pipelines Construction Works
Contact
Q PLUS AŞ. 2 PIECES TANK CONSTRUCTION MALATYA 2019
Home
»
Projects
»
Finished Projects
Finished Projects
809
EMPLOYER
:
Oralgaz AŞ.
PROJECT NAME
:
Malatya Filling Facility Tank Construction and Piping Works
PROJECT LOCATION / DATE
:
Malatya / 2019
PROJECT DURATION
:
90 (Days)
PROJECT DETAIL
:
2x 2.500 M3 Storage Tanks, Canopy, Steel Fabrication and Piping Works
Similar Threads
BUEN ARITMA TANK MALZEME +İMALAT İŞİ-ABHAZYA-2021
SİCİM SPA WEST QURNA – 2 PRODUCED WATER FACİLİTY PROJECT
GEMONT AŞ. SASA PTA TANK DİZAYN, İMALAT VE MONTAJ İŞLERİ- ADANA-2021
GLOBAL TERMİNAL 3X3600 M3 TANK İMALAT VE MONTAŞ İŞİ-DÖRTYOL-HATAY
TPAO 1 ADET 150.000 BBL KAPASİTELİ SİLİNDİRİK DİKEY TANK BORULAMA SİSTEMİ YAPIM İŞİ-BATMAN TERMİNALİ- BATMAN-2021