KAR GRUP ERBİL RAFİNERİ 25 PIECES TANKS CONSTRUCTION ERBİL IRAQ 2015

KAR GRUP ERBİL RAFİNERİ 25 PIECES TANKS CONSTRUCTION ERBİL IRAQ 2015
EMPLOYER:KAR GRUP
PROJECT NAME:Erbil Rafineri 4. Faz
PROJECT LOCATION / DATE:Erbil – Iraq / 2015
PROJECT DURATION:300 Days
PROJECT DETAIL:5 X 20.000 m³-4 X 12.000-2 X 10.000 m³-2 X 7.000 m³-2 X 6.000 m³-2 X 5.000 m³-1 X 4.000 m³-2 X 3.000 m³-3 X 1.500 m³-1 X 500 m³-1 X 200 m³ Storage tanks with a total capacity of 220,000 m³. Manufacturing-Assembly-Painting-Cathodic protection-Grounding-Lighting-External floating ceiling-Insulation-Fire system and tank instruments.